EDF x Ineo Nucléaire
Security and Site Protection Program
Location: multisite
Duration: 1.5 years
10,000 hours of study
40,000 hours on-site
The Issues
- Bring the physical protection systems at nuclear sites into compliance;
- Complete the work and commission the 6 sites within 87 weeks.
Solutions
A comprehensive and integrated solution with significant production capacity to meet compliance milestones across multiple sites simultaneously, for the design and construction work to reinforce the Enhanced Protection Zone:
- On-site surveys;
- Design and construction studies related to security and surveillance systems (IES);
- Installation and connection of IES equipment;
- Commissioning of the system.